Subject

    Quantitative Aptitude

    Topic

    Time and Work

    Three men can do as much work as 5 boys; and the wages of 3 boys are equal to those of 2 men. A work on which 40 boys and 15 men are employed takes 8 weeks and costs Rs.15750. How long would it take if 20 boys and 20 men were employed, and how much would it cost?

    ক)
    6 weeks; Rs. 14356.75 p
    খ)
    9 ¾ weeks; Rs. 15356.25 p
    গ)
    12 weeks; Rs. 16365.25 p
    ঘ)
    15 weeks; Rs. 17345.75 p
    ঙ)
    None of these

    Explanation

    Let the work of men be M and work of boys be B and their wages be wm and wb Given 3 men can do as much work as 5 boys and wage of 2 men is equal to wage of 3 boys ∴ 3M = 5B ⇒ M = 5B/3 And 2w m = 3w b ⇒ w m = 3w b /2 40 boys and 15 men work for 8 weeks to complete a job and the work costs 15750 Total work done = 40B + 15M ⇒ Total work done = 40B + 15 × 5B/3 ⇒ Total work done = 65B Thus to complete 65B work 8 weeks are required Total wage = 40w b + 15w m ⇒ Total wage = 40w b + 45w b /2 = 125w b /2 Given Total cost of work = 15750 Total cost = wage × number of weeks 15750 = 125w b /2 × 8 ⇒ w b = 31.5 If 20 men and 20 boys work then Total work = 20M + 20B ⇒ Total work = 20 × 5B/3 + 20B ⇒ Total work = 160B/3 To complete 65B work it took 8 weeks ∴ To complete 160B/3 time taken = 8160B3×65B\frac{8}{{\frac{{160B}}{3}}} \times 65B ⇒ Time taken to complete 160B/3 work = 39/4 = 9 ¾ Weeks Total wage = 20w m + 20w b ⇒ Total wage = 30w b + 20w b = 50w b Total cost = wage × number of weeks ⇒ Total cost = 50 × 31.5 × 39/4 ⇒ Total cost = 15356.25
    The number  of days in which A and B together can finish a piece of work is 12 days less than the time taken by A alone and 27 days less than the time taken by B alone to finish the work. If A and B completed the work in 15 days with the help of C and got a total compensation of Rs 3000 for the work, then what is the share of C?5 men and 5 women earn Rs. 660 in 3 days. 10 men and 20 women earn Rs. 3500 in 5 days. In how many days can 6 men and 4 women earn Rs. 1060?Two pipes can fill a tank in 5 minutes and 6 minutes respectively and a third pipe empties the full tank in 10 minutes. How much time will be taken to fill the tank if all pipes open simultaneously?8 men can complete a piece of work in 20 days.8 women can complete the same work in 32 days.In how many days will 5 men and 8 women together complete the same work?Two pipes fill a tank in 20 and 24 minutes respectively and a waste pipe can empty 3 gallons per minute. All the three pipes working together can fill the tank in 15 min. The capacity of the tank is?5 men and 2 boys working together can do four times as much work as a man and a boy.Working capacities of a man and a boy are in the ratio:P alone can complete a piece of work in 6 days and Q alone can complete the same piece of work in 12 days. In how many days can P and Q together complete the same piece of work?Jason won some goldfish at the state fair. During the first week 1/5 of them died and during the second week, 3/8 of those still alive at the end of the first week died. What fraction of the original goldfish were still alive after two weeks?

    Find Tutors

    View all Tutors