Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% of the work had been completed. How many additional workers will Mr. Jamal need to finish the work in time?
Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% of the work had been completed. How many additional workers will Mr. Jamal need to finish the work in time?
ক)
100খ)
50গ)
40ঘ)
35Explanation
50 workers in 20 days can do 1/2 of the job 1 worker in 1 day can do 1/(2*50*20) of the job = 0.0005 of the job Now, 0.0005 job can be done in 1 day by 1 worker 1/2 job can be done in 10 day by 1*0.50/(10*0.0005) worker = 100 workers So, additional worker needed = (100 - 50) workers = 50 workersRelated questions
The decimal number equivalent of (1010)2is-In a computer, which one of the following devices is capable of storing only a single bit?“ শাখের করাত” বাগধারাটির অর্থ কি?সন্ধি বিচ্ছেদ করুনঃ “ তিরস্কার”I do not like a person who hankers——wealth.MS PowerPoint is an example of which one of the following?“সূর্য” এর প্রতিশব্দ কোনটি?Which of the following is the odd one?