    A can complete a project in 20 days and B complete the same project in 30 days. If A and B start working in the project together and A quits 10 days before the project is completed, in how many days  will the project be completed?

    ক)
    14 days
    খ)
    15 days
    গ)
    18 days
    ঘ)
    27 days

    Explanation

    ধরা যাক , x দিনে কাজটি complete হয়েছে  B কাজ করেছে   x  দিনে  A কাজ করেছে   x-10 দিনে প্রশ্নমতে, x-10/20+x/30=1  or, 5x-30 =60  or,x=18